
Miroslav Stanković
ABSTRACT: Power Distribution Network Development Planning in the Belgrade Distribution Area
The distribution network development planning in the Belgrade Distribution Area was preceded by extensive work on the development of simulation models of the network for different operating conditions. The models were created using the Tokovi snaga software package and represent the maximum non-coincident demand of 110/x kV substations during both winter and summer periods. Using these models, the existing network condition was analysed. The analysis included the assessment of loading levels of all medium-voltage network elements, voltage conditions throughout the distribution system, and verification of compliance with the N-1 criterion for all relevant network elements. The results of the analysis identified several network constraints in the Belgrade Distribution Area, including elements operating above the limits defined in the Distribution System Operation Rules, voltage deviations beyond the ±10% nominal voltage limits, contingencies of elements for which secure supply cannot be ensured, and power losses on all 10 kV, 20 kV and 6 kV feeders supplied from 110/x kV and 35/10 kV substations. In order for the existing distribution network to accommodate future loads, while also considering the integration of distributed energy resources, a load forecast for both existing and future electricity consumers was developed for each stage of the planning period (2026–2033, with an outlook to 2043). The load forecast was defined for several consumer categories: households, directly forecasted customers, and other commercial customers (customers connected at 35 kV, customers connected at 10 kV, small commercial customers, and public lighting). The category of directly forecasted customers includes existing consumers whose annual electricity consumption exceeded 2,000,000 kWh in the previous year or whose measured maximum demand exceeded 500 kW. It also includes future consumers with an approved coincident load above 500 kW and a confirmed network connection. For consumers whose future connection is uncertain or whose commissioning timeline is not yet defined, a separate group of forecasted loads was formed. This load forecasting approach made it possible to analyse the spatial distribution of future loads based on the relationship between electricity consumers and their supplying MV/LV substations or measurement points. Based on the load forecast and the condition of the existing network, a set of investments required to be implemented by the end of the planning horizon (2033, with an outlook to 2043) was defined to ensure that the future network meets all technical criteria. The proposed investments include the construction of new 110/x kV and 35/10 kV substations, as well as underground cable and overhead lines at voltage levels of 35 kV, 20 kV, and 10 kV. As a result, the target network configurations for 2033 and 2043 were defined. The implementation timeline for each investment was determined using a proposed investment prioritization methodology. The methodology considers investments aimed at relieving network constraints, replacing aging network assets, and ensuring compliance with the N-1 security criterion. In addition, investments were categorized according to the type of distribution network element involved, such as transformers (110/x kV and 35/10 kV), cable lines, bundled conductors, and overhead lines at voltage levels of 35 kV, 20 kV, and 10 kV. Each investment was assigned a weighting factor based on the reason for its implementation and the type of element being installed. This approach enables the definition of prioritized investment sets for each stage of the planning period. In addition to the network development planning process, further analyses were performed to assess the network capacity for integrating renewable energy sources, the potential for connecting electric vehicle charging infrastructure, and the expected impact of heat pumps on the distribution network.
Keywords: distribution networks, power flow modelling, load forecasting, network development planning
ABSTRACT: Distribution network hosting capacity for connecting distributed energy resources (DER) in the Belgrade consumption area
The hosting capacity analysis enables the assessment of the feasibility of adding distributed energy resources (DER) and connecting them to different busbars in the network without violating the technical operating limits of the system. The results of the analysis allow network operators to identify critical points in the network (“bottlenecks”), evaluate the need for network reinforcement, and plan the optimal integration of new energy sources. The energy transition and the push for green energy imply an increasing share of renewable energy sources in electricity generation. However, connecting a new power plant to the system can cause reverse power flows in the network, exceedances of permissible voltage limits as defined by the Distribution Grid Code, overloading of the elements in the system, or degradation of power quality due to power electronic devices through which these sources are typically connected to the grid. In addition, planning production from renewable energy sources is a challenging task due to the intermittency of their output, which is directly influenced by natural conditions (cloud coverage, irradiation, ambient temperature, etc.). Precisely because of the stochastic nature of DER, for a relevant assessment of hosting capacity, as well as identifying locations in the system where congestion may occur, it is important to consider not only two operational scenarios (minimum and maximum) and fixed DER generation, but also the temporal correlation between solar generation on one side and consumer load on the other. Such analysis over time series also allows for a better understanding of potential operational constraints that need to be imposed on DER to ensure safe and reliable system operation. For these reasons, the hosting capacity calculation was performed using an hourly time series for a characteristic day, based on a 35/10 kV/kV distribution substation in Belgrade. The potential solar power generation was estimated based on the substation’s geographical location and meteorological insolation data. The network capacity analysis for integrating renewables was carried out through an iterative process, adding new MW of installed capacity to the nodes of the analyzed 35/10 kV/kV consumption area without proposing additional network infrastructure reinforcement or violating system technical limits. During the analysis, voltage and thermal limits of relevant network elements were respected, as well as the permissible voltage variation at the connection point, in accordance with the Distribution Grid Code. The results are presented in tabular form and graphically as heat map diagrams.
Keywords: hosting capacity, DER, simulation model, time-series
Biography of the presenter
Miroslav Stanković (born on June 30, 1980) is a graduate electrical engineer with extensive experience in the field of power systems. He graduated in 2006 from the Faculty of Electrical Engineering, University of Belgrade, majoring in Power Systems. Since 2007, he has been employed at the Nikola Tesla Electrical Engineering Institute in Belgrade, where he works as an Expert Advisor in the field of power systems. During his professional career, he has been engaged in modeling elements of power systems, power flow and system security analyses, as well as techno-economic analyses aimed at optimizing the operation of electrical power networks. His work particularly focuses on analyses of electricity and power consumption parameters, load forecasting, long-term development and planning studies of power systems, as well as projects related to the reduction of electrical energy losses and the improvement of energy efficiency in distribution systems. He has participated in the preparation of several significant national and international studies and projects related to the development and analysis of power networks. He is a member of the Engineering Chamber of Serbia, as well as the Serbian National Committees of CIRED and CIGRE. He actively uses several specialized software tools for power system analysis.

